Figure 45. Rotating frame ring gear, removal and installation.
j. Install the hydraulic oil lines and cylinders (TM 5-
m. Install the front and rear rollers assemblies (TM
3810-207-20).
5-3810-207-20).
k. Install the operating controls (TM 5 8810-207-
n. Install the front end attachments (TM 5-3810-
20).
207-20).
Section VIII. ROTATING FRAME RING GEAR
166. General
167. Rotating Frame Ring Gear Removal
a. Remove the front end attachments (TM 5-3810-
A dual flanged center, hub-type ring gear, is bolted to the
carrier frame and serves as the swing or tracking gear in
207-20).
b. Remove the crane rotating frame base assembly
which the crane assembly rotating gear and rollers
operate.
TAGO 5030A
90