TM 5-3810-306-20
Section II. SERVICE UPON RECEIPT
SUMMARY
The Container Crane is shipped in an "operation-ready" condition requiring no maintenance or operator actions. However,
it is recommended that a visual inspection of each system be made to ensure air, hydraulic, fuel, and coolant lines or
fittings have not loosened or been damaged during transit from the
manufacturer.
UNPACKING
The following should be used as a check list while unpacking the container Crane;
1.
Remove the restraining strap on the cab door.
2.
The fire extinguisher must be removed from the tool box and placed in the mounting bracket located in the cab.
CHECKING UNPACKED EQUIPMENT
a.
Inspect the equipment for damage incurred during shipment. If the equipment has been damaged, report the
damage on Form DD Form 6, Packaging Improvement Report.
b.
Check the equipment against the packing slip to see if the shipment is complete. Report all discrepancies in
accordance with the instructions of DA PAM 738-750.
c.
Check to see whether the equipment has been modified.
DEPROCESSING UNPACKED EQUIPMENT
The container crane should be clean and free of excess grease. However, if during inspection, any excess grease or
lubricant is found on the carrier frame or superstructure it should be cleaned immediately.
2-2