TM 5-3810-289-12
(2) Operating pedals. Refer to paragraph
2-5a (2).
(3) Crowd clutch linkage.
Refer to
paragraph 2-3b (5).
(4) Forward drum brakeband. Refer to
paragraph 2-3b (6).
(5) Backhoe boom installation.
(a) Build cribbing to support backhoe
(b) Propel machine forward until boom
feet enter lugs on revolving frame. Use jack to raise or
lower boom until aligned.
(c) Install boom foot pins and locking
bolts.
(a) Place auxiliary A-frame in lugs on
revolving frame.
(b) Install pins and locking bolts.
(7) Auxiliary A-frame suspension cable reeving
length.
(b) Lead cable over right auxiliary A frame
sheave.
(c) Lead cable around A-frame yoke sheave
and under left auxiliary A-frame sheave.
(d) Lead cable over left A-frame sheave and
attach to boom hoist drum.
(e) Attach other end to anchor on A-frame.
(8) Roller and spacer assembly arrange mert.
(a) Model 22BM craneshovel roller and
Figure 2-10. Dragline fairlead, removal and installation.
(b) Spacers and shaft dimensions are
2. Lead cable over right boom point
sheave.
(a) Hoist cable.
3.
Reeve cable through clamshell
1. Refer to table 4-3 for correct cable
sheave and anchor.
length.
4. Attach other end to front drum.
2. Lead cable over right center A-
(d) Tagline cable.
frame sheave.
1. Lead cable from tagline unit over
3. Lead cable under and around dipper
sheave to bucket.
handle sheave over the left center A-frame sheave and
2. Anchor end to clamshell bucket,
attach to hoist drum.
(10) Tagline unit adjustment (fig. 2-13)
4. Attach other end to anchor on
Turn cable wheel counterclockwise to wind tag line
dipper handle.
spring.
b. Removal. Removal procedure is reverse of
installation.
2-7.
Backhoe Front End Conversion
a. Installation.
(1) Operating levers. Refer to paragraph
2-3b (3).
2-10