TM 5-3810-307-10
WARNING
Use care when stowing the hydraulic hoses onto the
boom hose reel as the hose reel is under tension. Do
not release the hydraulic hoses and allow them to
rewind onto the reel as this will allow the hoses to
swing freely until the tension on the reel is relieved.
b.
Disconnect hydraulic quick disconnect fittings at grapple. Then install caps
on quick-disconnect fittings. Unhook hose reel tag lines from grapple. Then
while maintaining the tension on the hose reel and rewind hydraulic hoses
onto hose reel. Hook the tag lines on their stowing ring. Cap open fittings
on cylinder of grapple.
c.
Disconnect grapple at its attachment point. Restore hook block to its original
configuration. Stow chain sling.
5-11.
INSTALLING CONCRETE BUCKET.
WARNING
Always calculate the total weight of the load, then
operate within the load chart parameters.
NOTE
When computing Load Chart Limits, the weight of
accessories must be added. Weights for the clamshell
(Load Chart). Weights of other accessories may be
found in the manufacturer's equipment manuals.
5-11.1
Installation.
a.
Place the concrete bucket on a firm, level surface.
b.
c.
Hook concrete bucket attachment point onto hook block.
Removal.
a.
Lower concrete bucket onto firm, level surface.
b.
Unhook concrete bucket attachment point from hook block.