TM 5-3810-207-20/TO 36C23-3-37-12
Figure 12. Engine flywheel timing works.
b.
Removal. Remove the starter solenoid
assembly as instructed on figure 15.
c.
Cleaning and Inspection.
(1) Clean the starter solenoid with a cloth
dampened with an approved cleaning
solvent.
(2) Inspect
the
solenoid
for
proper
operation and other damage. Replace
defective solenoid.
(3) Inspect the wiring for frayed, broken, or
worn conditions. Replace wiring as
necessary.
d.
Installation. Install the starter solenoid as
illustrated on figure 15.
78. Starter Assembly
a.
Removal.
(1) Remove the starter solenoid (par. 77).
(2) Remove the starter as instructed on
figure 15.
b.
Cleaning and Inspection.
(1) Clean the starter assembly with a 40
cloth dampened with an approved
cleaning solvent (2) Rotate the drive
pinion to see that the armature turns
freely and does not bind.
(3) Remove the cover band and inspect the
brushes. If brushes are worn to less
than 1/2 inch of the original length,
replace brushes.
(4) Inspect starter assembly for proper
operation, wear, and other damage.
Replace defective starter.
(5) Inspect the commutator for pits, burns,
and other damage. If commutator is
defective, replace starter.
c.
Installation. Install the starter assembly as
illustrated on figure 15.
d.
Brush Replacement.
(1) Removal.
(a) Remove the starter as instructed on
figure 15.
(b) Remove the cover band.
(c) Remove the brushes as instructed
on figure 16.
(2) Installation.
(a) Install the brushes as illustrated on
figure
16.
Fit
brushes
to
commutator.
(b) Install the cover band.
(c) Install the starter -as illustrated on
figure 15.
79. Instrument Panel Components
a.
Removal. Remove the instrument panel
components as instructed on figure 17.
b.
Cleaning and Inspection. Clean and
inspect. Replace damaged or defective instrument
panel components.
c.
Installation. Install the instrument panel
components as illustrated on figure 17.
80. Oil Pressure Sending Unit, Safety Switch, and
Pressure Switch
a.
Removal. Remove the oil pressure sending
unit, safety switch, and pressure switch as instructed on
figures 17 and 18.
b.
Cleaning and Inspection. Clean and
inspect. Replace defective sending unit and switches.
40