TM 5-3810-305-23
0024
INSTALLATION - Continued
12.
Using two new cotter pins (Figure 30, Item 1) connect two control cables (Figure 30, Items 2 and 5) to
transmission control valve (Figure 30, Item 6). Tighten two jam nuts (Figure 30, Item 4) on each cables to
mounting bracket (Figure 30, Item 3). Check and adjust cables (WP 0086).
2
1
3
4
6
5
M0062105
Figure 30.
Power Pack Installation.
13.
Connect two hoses (Figure 31, Items 1 and 3) to ground driven steering pump (Figure 31, Item 2).
1
2
3
M0061105
Figure 31.
Power Pack Installation.
0024-25
03/15/2011Rel(1.8)root(maintwp)wpno(M00029)