TM 5-3810-305-23
0076
INSPECTION
1.
Inspect parts IAW General Maintenance Instructions (WP 0162).
2.
Inspect battery cables for broken, cracked, or deteriorated insulation.
3.
Inspect battery cable terminal for corroded or damaged condition.
4.
Inspect battery case for signs of cracks or electrolyte leakage.
5.
Ensure terminal posts are solid.
6.
Replace battery cables that have broken wires or damaged insulation.
7.
If battery is to be charged, observe all safety precautions. Charge batteries (refer to TB 9-6140-252-13).
8.
Inspect all other parts.
END OF TASK
INSTALLATION
1.
Install slave receptacle (Figure 8, Item 10), four bolts (Figure 8, Item 9), new lockwashers (Figure 8, Item 8),
and nuts (Figure 8, Item 7) on battery box.
2.
Install shunt (Figure 8, Item 3), two bolts (Figure 8, Item 6), new lockwashers (Figure 8, Item 5), and nuts
(Figure 8, Item 4) on battery box.
3.
Connect blue and red wires to shunt (Figure 8, Item 3) and install two new lockwashers (Figure 8, Item 2) and
screws (Figure 8, Item 1) on shunt.
1,2
3
4,5,6
7,8,9
10
M0097105
Figure 8. Battery and Cables Assembly Installation.
03/15/2011Rel(1.8)root(maintwp)wpno(M00082)