OUTRIGGER ASSEMBLY MAINTENANCE
Figure 1. Outrigger Assembly Removal.

Technical Manual For Crane, Wheel Mounted, Hydraulic, Light, 7 1/2 Ton Page Navigation
  781    782    783    784    785  786  787    788    789    790    791  
img
TM 5-3810-305-23
0123
REMOVAL
1.
Fully extend and lower all outriggers without putting any pressure on outrigger pads (TM 5-3810-305-10).
WARNING
Weight of beam is approximately 129 lb (59 kg). Use adequate lifting equipment to lift and
support beam. DO NOT lift over personnel or let personnel walk underneath suspended load.
Failure to follow this warning may cause injury or death to personnel.
NOTE
The following is a maintenance procedure for one outrigger assembly. The maintenance
procedure for the remaining outrigger assemblies is identical.
2.
Support cylinder and beam (Figure 1, Item 1) with suitable lifting device.
3.
Remove pin (Figure 1, Item 3) from pin (Figure 1, Item 2).
4.
Remove pin (Figure 1, Item 2) from
beam (Figure 1, Item 1).
5.
Remove capscrew (Figure 1, Item 7), lockwasher (Figure 1, Item 6), and rod end (Figure 1, Item 9).
Discard lockwasher.
6.
Remove pin (Figure 1, Item 8) from beam (Figure 1, Item 1).
7.
Remove beam (Figure 1, Item 1) from frame.
0123-2
03/15/2011Rel(1.8)root(maintwp)wpno(M00138)