INSTALLATION
1.
Install strip (Figure 2, Item 1), bracket (Figure 2, Item 6), and four new locknuts (Figure 2, Item 2) onto boom.
2.
If removed, apply threadlock compound to cam follower (Figure 2, Item 7) and press into bracket
(Figure 2, Item 6) until the stud end of cam follower is 0.03 inch (0.8 mm) below the surface of bracket.
3.
Install spacer (Figure 2, Item 4), pendulum (Figure 2, Item 5), and new locknut (Figure 2, Item 3) on bracket
(Figure 2, Item 6). Tighten locknut to 21 ft-lb (28 Nm).
1
2
3
4
7
5
6
M0595105
Figure 2.
Boom Angle Indicator Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Connect battery cables (WP 0076).
2.
Place boom in resting position (TM 5-3810-305-10)
3.
Check for proper operation.
END OF TASK
END OF WORK PACKAGE