Figure 3. Axle Lockout Valve Adjustment.
Figure 2. Boom Hoist, Winch, and Outrigger Valve Controls Removal.

Technical Manual For Crane, Wheel Mounted, Hydraulic, Light, 7 1/2 Ton Page Navigation
  922    923    924    925    926  927  928    929    930    931    932  
img
. . . . . . . . . .
TM 5-3810-305-23
0138
FIELD MAINTENANCE
BOOM HOIST, WINCH, AND OUTRIGGER VALVE CONTROLS MAINTENANCE
INITIAL SETUP:
References
Tools and Special Tools
WP 0162
Tool Kit, General Mechanic's (WP 0171, Table 1,
Item 17)
Equipment Condition
Boom in horizontal position and fully retracted (TM
Materials/Parts
5-3810-305-10)
Pin, Cotter M2X12MM (WP 0172, Table 1, Item
Outriggers lowered and fully extended (TM
155) Qty:  3
5-3810-305-10)
Pin, Cotter 3X30 (WP 0172, Table 1, Item 156)
Dash panels removed (WP 0066)
Qty: 3
Battery cables disconnected (WP 0076)
Rag, Wiping (WP 0170, Table 1, Item 52) Qty: 1
Washer, Split M8 (WP 0172, Table 1, Item 95)
Qty: 2
REMOVAL
1.
Remove three cotter pins (Figure 1, Item 3) and pins (Figure 1, Item 4) to disengage yokes (Figure 1, Item 1)
from handles (Figure 1, Item 2). Discard cotter pins.
2
1
4
3
M0484105
Figure 1. Boom Hoist, Winch, and Outrigger Valve Controls Removal.
0138-1