Figure 5. Boom Hoist, Winch, and Outrigger Valve Controls Installation.
SWING/TELESCOPE VALVE CONTROLS MAINTENANCE

Technical Manual For Crane, Wheel Mounted, Hydraulic, Light, 7 1/2 Ton Page Navigation
  928    929    930    931    932  933  934    935    936    937    938  
img
. . .
TM 5-3810-305-23
0138
INSTALLATION - Continued
4.
Position three yokes (Figure 6, Item 1) on end of handles (Figure 6, Item 2).
5.
Install three pins (Figure 6, Item 4) and new cotter pins (Figure 6, Item 3).
2
1
4
3
M0484105
Figure 6. Boom Hoist, Winch, and Outrigger Valve Controls Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Connect battery cables (WP 0076).
2.
Install dash panels (WP 0066).
3.
Place boom in resting position (TM 5-3810-305-10).
4.
Outriggers retracted and raised (TM 5-3810-305-10).
5.
Check for proper operation.
END OF TASK
END OF WORK PACKAGE
0138-7/8 blank