e.
Slowly rotate hoist drum in raise direction,
ensuring first layer of wire rope is evenly wound
onto drum and all wraps are tight.
NOTE
Use of a rubber mallet may be needed
to tap on wraps to ensure they are
tight together.
f.
Continue to wind remainder of wire rope on hoist
drum slowly, maintaining an even tension on
wire rope.
2.
CABLE REEVING FOR HOOK BLOCK (MAIN
WIRE ROPE):
NOTE
To reeve the hook block, the
auxiliary boom nose anti-two block
connection must be unplugged and
the auxiliary boom nose unpinned on
the right side (facing forward) and
swung to the left.
a.
Allow a sufficient length of cable to be removed
from main hoist.
b.
Position cable over upper boom nose sheave
and then route through remaining sheaves as
shown.
c.
Install hook block. (Refer to page 17-7.) d.
Swing auxiliary boom nose in place and secure
with pin and clip.
d.
Connect anti-two block jumper cable.
3.
CABLE
REEVING
FOR
OVERHAUL
BALL
(AUXILIARY WIRE ROPE):
NOTE
Lifting capacity of auxiliary hoist with
a single part line over auxiliary boom
nose is limited to 4.5 tons (4082 kg).
a.
Allow a sufficient length of cable to be removed
from auxiliary hoist.
b.
Position cable over upper boom nose sheave
and then route over auxiliary boom nose sheave
as shown.
c.
Install overhaul ball. (Refer to page 17-4.)